Someone on holiday shouldn't get a status question. That is why FlowLoop checks shortly before every send whether the person should be asked at all on that day. There are two ways: the pause you set in FlowLoop, and the absences from FlowTime, which FlowLoop takes into account on its own.
Absences from FlowTime
If your team uses FlowTime, FlowLoop reads the approved absences. A person gets no question on a day if one of these absences is approved for that day:
- a full-day vacation,
- a full day of sickness,
- a full-day business trip,
- two approved half days that together cover the whole day, morning and afternoon.
A single half day, a request that hasn't been approved yet and overtime reduction have no effect. On such days the question goes out as usual.
The run then shows Skipped for the person. They don't get a question for this date later either, and on the next date after the absence everything continues normally. How absences are requested and approved is explained in Request and report absences.
Set a pause
For anything that isn't in FlowTime, set a pause, for example for parental leave, a project phase on site with a customer, or if you don't use FlowTime.
- In FlowLoop, open Team members.
- Click the pencil icon (Edit details) in the person's row.
- Under Pause until, enter the last date on which the person shouldn't be asked. The day itself counts.
- Click Save.

The list shows Paused until with the date next to the switch. After that day, FlowLoop asks again automatically, you don't need to reset anything. More about the details per person in Set notes, language and a pause.
When else nobody is asked
- Participation switched off: anyone not switched on in the Participation column is never asked.
- Left the team: if someone leaves the team, their participation ends automatically.
- Introduction not yet delivered: the introduction email must have arrived before the first question.
- Schedule paused or changed: questions still planned under the old rule no longer go out.
Good to know
- The check happens at sending time. If an absence is approved or the pause is set shortly before the date, it still takes effect as long as the question hasn't been sent yet.
- No notes to the manager: skipped dates don't count as unanswered questions. So after a holiday, the daily notes email won't report that someone didn't reply.
- Response rate: skipped questions don't count in the overview either.
Troubleshooting
- Someone got a question on holiday anyway: check in FlowTime whether the absence is approved and covers the whole day. An open request or a half day isn't enough. Otherwise set a pause.
- Someone gets no more questions after their holiday: check under Team members whether Paused until still shows a later date or the switch is off. Other causes are listed in No questions arrive or replies are missing.